An overhead view of the Edgewater Bridge provided by the City of Everett.
The design process is complete for the Edgewater Bridge replacement. The project was advertised to potential contractors on May 16, 2023, with an anticipated bid opening in June 2023. Award and Notice to Proceed will take place in July 2023.
Once roadwork begins, West Mukilteo Boulevard will be closed between Mukilteo Lane/LaMar Drive and Shore Avenue for approximately 12 months.
For questions related to the project: please contact the principal engineer Dan Enrico at 425-257-8981 or denrico@everettwa.gov.
We encourage you to share this information with your neighbors. For information about your neighborhood group, including meeting times, visit everettwa.gov\neighborhoods.
For more information about this project and to sign up for project updates, visit the everettwa.gov/edgewater.